Parc éolien offshore “DolWin6” à courant continu

900 MW

maximum output generated of wind turbines

2×90 km

de câbles sous-marins

Partenariat

TenneT

Marché

Parcs éoliens offshore

Localisation

Allemagne

offshore wind farm

Contexte

In July 2017, transmission system operator TenneT awarded Nexans the contract to supply and install the cables for the DolWin6 direct-current link. This project aims to transport electricity from the offshore wind farms of North Sea Cluster 3 from the DolWin Kappa HVDC converter station to the Emden/Ost onshore HVDC converter and transformer station. The project involved the installation of two parallel, XLPE-insulated 320 kV DC cables, each measuring 90 km in length, with a maximum output capacity of 900 MW. The project, valued at around 100 million euros, was completed in 2023 and represents one of Nexans Deutschland’s largest projects.

Défis

The geographical location of the offshore wind farm presented challenges, as the cables must pass through the ecologically sensitive Wadden Sea. Additionally, the cables cross the island of Norderney, necessitating careful installation techniques to protect the environment and wildlife.

Key figures

900 MW

Maximum output generated by wind turbines

2×320 kV

Maximum voltage of the cables

2×90 km

longueur de câbles sous-marins

Contribution de Nexans

Nexans was responsible for all stages of the project related to the cable system, including design, manufacture, logistics, and installation. The Group supplied submarine XLPE-insulated 320 kV DC cables, manufactured in Norway, accessories, and installation services. Additionally, Nexans installed a fiber-optic cable for data transfer.

Land cables, produced in Belgium, were installed between Hilgenriedersiel and Emden at a distance of roughly 45 kilometers.

Low-loss high-voltage and ultra-high-voltage cables from Nexans enable grid operators to expand their grids in a way that achieves the best possible results in terms of efficiency and conservation of resources, and thereby to lay the groundwork for the energy supply of the future.

Je me réjouis que TenneT nous ait attribué le contrat pour cette importante liaison. Nous avons été chargés de toutes les étapes du projet DolWin6 relatives au système de câblage, parmi lesquelles la conception, la fabrication, la logistique et la pose. Après des projets comme Beatrice, Italie-Montenegro et NordLink, voici une nouvelle occasion de faire valoir nos compétences en matière de transport du courant continu haute tension.

Directeur général, Nexans Allemagne

offshore-dolwin

En savoir plus sur les solutions Nexans

Parcs éoliens offshore

Découvrir nos réalisations

offshore-wind-north-sea-thumbnail

Parcs éoliens offshore

Saint Brieuc : l’un des plus importants projets français d’éolien offshore
offshore wind farm - Nexans employee

Parcs éoliens offshore

Parc éolien offshore “DolWin6”
thumbnail-hywind

Parcs éoliens offshore

Hywind Scotland : le premier parc éolien flottant