Case study

Horns Rev 1

  • LIEU
    Denmark
  • PARTENAIRE
    Eltra
  • MARCHÉ
    Fermes éoliennes-Offshore
160 MW

GENERATED OF WIND TURBINES

170 + 33 kV

MAXIMUM VOLTAGE

42 km

OF OFFSHORE CABLES

About the project

As the world's leading wind-power nation, Denmark has decided to take yet another step forward and install larger, more powerful windmill parks further out to sea than ever before. The first facility is to be built at Horns Rev and will consist of 80 windmills, each of 2 MW. This sea-based windmill park will start supplying electricity from July 2002.

Nexans has been awarded a contract from Eltra in Denmark, an electricity transmission company based in Jylland/Fyn (Denmark), to deliver and install 21km of subsea power cable to the world's largest sea-based windmill park, Horns Rev, by the Danish west-coast.

Nexans' solutions

Nexans delivered and installed the world's most powerful three-conductor AC cable: a 150 kV underwater power cable going directly into Eltra's electricity transmission system on land. Due to its transmission capacity and size manufacturing this cable was a major professional challenge. Nexans beat the stiff competition for this contract mainly due to its wide-ranging offshore experience.

 

 

 

Layer 1
Marché associé
Éolien offshore Découvrir

Contactez-nous

Sujets sur lesquels vous souhaitez obtenir plus d'informations :

* Champs obligatoires

Veuillez vérifier votre saisie et réessayer.

Une adresse mail ne peut contenir qu'un seul @

Protection des données personnelles

Vous avez le droit de vous opposer au traitement de vos données personnelles et/ou à leur utilisation à des fins de marketing direct ou à des fins commerciales.

Merci !

Merci de nous avoir contactés. Nous vous contacterons sous peu.

Erreur

Une erreur s'est produite. Veuillez réessayer.

Fermer